Build Progress

Friday, 31 October 2014

Halloween Present.

The Finishing Kit finally was delivered today. I helped the driver unload it from the truck and took it into the hangar. Came back with Campbell in the evening to unpack and inventory the finishing kit.

Total time: 1.5 hours.

Wednesday, 29 October 2014

Flaps and clean up

 Campbell helped clean out the hangar today and we made a spearate table for parts, tools and the workbench. Once that was done we bolted the Flap System in place. Not bad for an afternoons worth of work.
 
Total time: 3 hours.
 
 
 

Tuesday, 28 October 2014

Tail Cone Final Attach Begins

Curtis and I started riveting the pieces together and got the F-1006-B Bulkhead riveted to the F-1006-A and C.

Total time: 2 Hours

Sunday, 26 October 2014

Sunday work

Curtis and I got to working on the bulkhead and deburring the match drilled holes in the fuse tail meet section. I went home for lunch and groceries and got back to the hangar for deburring. All done we are ready to put the two pieces together for the final time and start riveting.

Total time: 4 hours.

Saturday, 25 October 2014

Match drilling Fuse and Tail

We just about got to match drilling the fuse and tail and Curtis asked me to get the safety glasses on.
I did and there was some debris in the glasses that went in my eye. I had to go to the walk in to get my eyes checked out. When I washed my eyes out the debris was gone but rubbing had made the eyes sore. Rest all evening

Time: 2 hrs

Friday, 24 October 2014

Friday work

We got some work done today. Managed to put together the Matco Parking brake valve together and rivet that to the fuselage.
I couldn't get the outboard end of the Flaps pushrod in the fuse there was too much griping with the bushings. (Thanks Curtis for cutting the bushings) Also the powder coating on the flap rod is thick enough to cause it not to fit together.
I got some of the crap vaccumed out of the baggage area. and we managed to get the tail cone top skin on. It's a 2 person job since the bulkhead was not lining up.


Time Spent: 3 hours.(Campbell included)


Tuesday, 21 October 2014

Seat Back A Complete

Curtis flattened the wrongly dimpled seat back and Campbell and I finished up with seat back A.
Looks good.

Total time : 2 hours.

Saturday, 18 October 2014

Saturday work

Nice work today. After attending Braithwaites Winter tune up seminar and getting some lunch got back to the hangar for some work. Got multiple jobs done in different areas.
  • Curtis was over and helped match drill the F-1019 - 20 - 21 baggage ribs to the F-1006B bulkhead.
  • Match drilled the Fuse longeron to the tail longeron.
  • Campbell helped countersick the Rear seat back (A) angles.
  • Pre-Assembled the Parking Brake Valve
  • Drilled out the old brake valve mounts to make way for the Matco Parking Brake valve.
 
Next steps is to separate the tail and fuse and deburr the holes and put it back together for final riveting.
 
Total time: 3 Hours.
 
 

Friday, 17 October 2014

Control columns mounted.

Mounted the Control columns today. Getting the washers in was a real pain. It took us over 3 hours just to get this done. Still have not mounted the aleron Pushrods and they are not aligned symmetrically...baby steps we will get there.
 
Total time : 3 hours. Thanks Campbell.


 

 
 
View of Co-Pilot Side

 
 
Sunday: Oct 19th Added F-1065  Push rod assembly to the Control Columns. Now they move together. Once I add the elevator push rod to the control column and the idler arm we will be done.
Total time : 1 hour.
 

Day off from the Build

Took the day off from the build Ended up getting voted to the EAA Chapter as the Vice President.

Wednesday, 15 October 2014

Seat back B complete.

I got to the hangar and tried bolting on the elevator idler arm. Could really get it right so I abandoned it for later. Fabricated the shim for the tail cone attach longeron. Campbell then showed up and we put together the seat back. Just got one done. Saved the other one for the weekend.
 
Thanks again Campbell. 
 
Time spent: 4hours

Saturday, 11 October 2014

Thanksgiving weekend.

Rear Seat Back Assembly.


Well it's the thanks giving weekend. 3 days home alone. Hopefully I can get a lot done on the fuse.
Thank good ness Curtis placed the heater in the hangar. I will bring the propane tank in today and it will be nice and toasty.
Campbell will show up later today and hopefully we can get the seat backs drilled out properly.

Campbell and I got a lot of work done today. We got one seat back match drilled and he managed to remove the top of the pilot seat assembly. Now I can proceed with the control column asssembly.

Total time 4 hours.

Dave stopped by with the staple gun and ladder. We are scheduled to meet on monday to put up the tarp.

I came back to the hangar today around 4pm and finished match drilling the other seat back.
Now to final rivet and put on the hinges.

Total time 2 hours.

Thursday, 9 October 2014

Rear Seat Backs

Started on the rear seats today. This should be easy to do.

Rear Seats.
  • Fabricate two F-637B R and two F-637B L using the 1/8th  angles provided. 26 3/8 in length.
  • Fabricate four F-637C angles of 16 inches in length using the 1/6th AL Angle.
  • Marked off the areas will set it up on the clamp and file down.

Friday Oct 10: 3 Hours. Continues work on the seat backs and Marked the drill holes on the seat back.
The WIERD spacing makes it hard and time consuming. Also cut off the four 16" F637C Angles.

Wednesday, 8 October 2014

Control System Assembly

Completed the assembly of the Elevator and Aileron Push Rods. As seen below.
Also completed the assembly of the elevator idler arm.
Positioned the F1090 push Rod onto the bell crank assembly in the tail.
Thanks for all the help Campbell:
Total time: 4 hours. 

Wednesday, 1 October 2014

Elevator Pushrods

Took the elevator pushrods to the EAA hangar to use their drill press. Match drilled all holes at both ends of both pushrods. F-1089 and F-1090. Deburred the holes and primed. Waiting for the rod to dry before reviewing ends in place. Campbell was a great help. While drilling the hole in the rod end the 1/16 drill bit broke. I had to come home and hammer it out with another bit. Luckily the hole was ok and we didn't have to drill another hole.

Time: 4 Hours. and another 3 hours on Oct 4th. F-1090 complete and primed. Set for drying. Shreyans cam to see the project was nice seeing him after a long time. Kelly showed up in the evening and we all had a nice dinner and back home for cake.
Thanks Guys.