Huge Milestone for today. Fuselage inspection all done. Pierre and Ritz were wonderful and it was a pleasure working with them.
Build Progress
Saturday, 28 March 2015
Sunday, 22 March 2015
Friday, 20 March 2015
Monday, 9 March 2015
Sunday, 8 March 2015
Saturday, 7 March 2015
Sunday, 1 March 2015
Rudder Pedals
Dismantled the rudder pedal assembly last night realized that the F-1039 bracket was not primed. Primed and left it out to dry came back this morning and final mounted the pedals.
Helped Curtis rivet the Baggage area side skin with the flange. Curtis torqued the final bolts on the gear mounts leg. Also routed the rudder cable through the gr omits in the tail.
Total time : 2 hrs.
Helped Curtis rivet the Baggage area side skin with the flange. Curtis torqued the final bolts on the gear mounts leg. Also routed the rudder cable through the gr omits in the tail.
Total time : 2 hrs.